Jagstberg I–IV: 35.66 MWp under construction

Projects · 06/11/2026 · 1 min read

Since August 2026, PHV Energy teams have been on site at Jagstberg I–IV in Germany, delivering the full installation scope of a 35.66 MWp utility-scale solar project built in four sections. Completion is planned for December 2026.

From mounting structures to commissioning: site progress seen from the air.

Our scope on site

  • Mounting structures and module installation: assembly of the mounting system and installation of the PV modules across all four sections.
  • DC and AC cabling: cable routing, laying, fixing and preparation for termination.
  • Commissioning support: QA/QC checks, corrections and support through testing and energization.

Project at a glance

  • Project: Jagstberg I–IV, Germany
  • Capacity: 35.66 MWp
  • Period: August – December 2026
  • Team on site: around 60 PHV Energy professionals

Photos from the site

Jagstberg is one of 34 utility-scale projects PHV Energy teams have worked on since 2021, with 432 MW of photovoltaic and battery storage capacity installed across Germany.

Planning a solar or BESS project and need an experienced installation partner? Contact our team to discuss your site, scope and schedule.